Elimination of PCB Liability Transformers, Capacitor Banks and Switch Replacement

Following an emergency response and remediation of a leak from a second floor substation transformer, SUNPRO was contracted to eliminate the remaining PCB liabilities including the retrofit of seven PCB transformers, replacement of 24 PCB capacitors and removal of four PCB switches. The transformers ranged fromĀ 100 kVA to 2000 kVA and were located in five substations, including rooftop and mezzanine locations. The work was coordinated over two shutdowns. SUNPRO provided all the new equipment, installation and rigging services, as well as transportation and disposal of the PCB materials.